2017 preRMO p3, team A needs 12 days, team B needs 36
Source:
August 9, 2019
algebraproblem
Problem Statement
A contractor has two teams of workers: team and team . Team can complete a job in days and team can do the same job in days. Team starts working on the job and team joins team after four days. The team withdraws after two more days. For how many more days should team work to complete the job?